2012.12.02 Russia YHZS75 Plant Installation Finished Successfully

2012-12-02
This customer started cooperation with us from June, 2012 and most parts of this project needed customization. Most demands were totally different from our standard production. For example, added one set vibrating screen on upper layer of batching machine to meet the requirement of local sand’s larger water content; and also added customer habitual operation modes in control software and some button.

About one week to finish whole plant’s design, via 25 days to complete production and take another 10 day’s test running to deliver plant successfully.

In November, customer required engineer fly to his project site for installation and commissioning.
After 35 days, finish installation and training smoothly.

Engineer professional guidance and serious working attitude won high evaluation from customer.
And also many local trading companies and government departments visited this project. 
                    
                               